Main Contractor: Indigo
Project Duration: 3 Weeks
Completion Date: 01/12/13
Project Brief: To design, supply and install new walk in coldrooms in two distribution hubs with disabled and mobile trolley access
Description: Indigo were appointed as the main contractor to undertake the works to transform existing kitchen production facilities into walk in cold rooms.
The works were to include for extending the existing storage facilities to allow for greater refrigerated food storage as well as new disabled and trolley ramps from the main car parks for ease of access.
The two RVS sites based some 60 miles apart were to be shut down at the same time for the works to be undertaken so project management was an essential part of the project.
Services Used:
- Cad Design
- Supply and installation of catering equipment
- Coldrooms and plant
- Building works
- Electrical works
- Supply and Installation of hygiene wall and floor coverings
- Project management
- On site health and safety